DEADLINE: 5TH JULY, 2021
FEDERAL REPUBLIC OF NIGERIA
FEDERAL MINISTRY OF WATER RESOURCES; CHAD BASIN DEVELOPMENT AUTHORITY
KM 6 DIKWA ROAD MAIDUGURI
INVITATION FOR TECHNICAL AND FINANCIAL BIDS FROM CONTRACTORS FOR THE EXECUTION OF 2021 MAINLINE CAPITAL DEVELOPMENT AND ZONAL INTERVENTION PROJECTS

(1.0) INTRODUCTION
(1.1) The Chad Basin River Development Authority in furtherance to achieving its statutory mandate intends to undertake the procurement of various works /goods under the 2021 mainline capital Appropriation and Zonal Intervention Projects domiciled to be implemented through the Authority in accordance with the provision of part VI section 25-2(ii) of the Public Procurement Act, 2007.

(1.2) The Chad Basin Development Authority, therefore, wishes to invite competent,interested contractors with relevant experience and technical expertise, financial capabilities, and good track record to submit Technical and Financial proposals in response to the bid documents to be issued to them for the execution of various projects categorized as follows:

(2.0) SCOPE OF WORKS
The scope of works and the specifications as contained in the Standard Bidding Document (SBD) to be issued to bidders in respect of each project. 

CATEGORY 1. CBDA MANDATE CORE PROJECTS

(A) WORKS

LOTSPROJECT DESCRIPTION
A1Construction of 1No. Solar Powered Boreholes in Potiskum Lga, Yobe State
A2Construction of 1no. Solar Powered Borehole In Kangleri Late Saina Bukar Chiteambe Area Bama Lga, Borno State
A3Rehabilitation of Guest House/Lodges At Ahq,
A4Rehabilitation Of 48nos. Senior Staff Quarters At Ahq
A5Rehabilitation Of 70nos. Intermediate Staff Quarters At Ahq
A6Rehabilitation Of 112nos. Junior Staff Quarters At Ahq
A7Partnership Program For Expanded Water Supply, Sanitation And Hygiene (Pe-Wash) ; Construction Of Vip Toilets And Provision Of Water Supply Facility in Borno State
A8Partnership Program For Expanded Water Supply, Sanitation And Hygiene (Pe-Wash); Construction Of Vip Toilets And Provision Of Water Supply Facility In Yobe State
A9Establishment Of 2nos. Hydrological Stations
A10Ground Water Development In Agro Service Centers In Projects And Area Offices ; (Construction Of 2nos. Solar Powered Boreholes)
A11Alau Dam Rehabilitation Works
A12Rehabilitation of Water Supply System And Reticulation Works At Ahq.
A13Erosion Control Work/Land Reclamation And Drainage Works in Borno, Yobe And North Part Of Adamawa States (Lagos Street, Maiduguri)
A14Completion Of Storage Facilities, Construction Of 2 Million Surface Tank and 1 Million Overhead Tank Complete with Accessories At Abari (Provision of Drainage At Abari Water Works)
A15Completion Of Reticulation And Control Structures At Abari (Connection Of Water Point To Houses)
A16Provision Of Drip Irrigation System In Arid Region Of The Authority
A17Rehabilitation And Upgrading Of Equipment/Plants At Water Bottling Plant In Borno State (Renovation Works)
A18Construction Of Water Control Structures At Jere
A19Construction Of Erosion And Flood Control Structures At Mubi
A 20Construction Of Dyke At Nyakire, Fune Lga – Yobe State
A21Construction Of 5nos. Solar Powered Boreholes At Selected
A22Construction Of Solar Powered Boreholes In Conflict Areas Of Borno States
A23Construction Of Solar Powered Boreholes In Conflict Areas Of Yobe States
A24Rehabilitation / Replacement Of Heavy Duty Earth Moving Machines (Repairs Of Dozer, Excavator And Grader
A25Reconstruction Works At Scip I New Marte
A26Construction Of Water Harvesting Structures In Chikuriwa Community Nangere Lga
A27Development Of Additional 300ha At Jere Bowl Irrigation Project (Irrigation Project Development, Procurement Of Tractor And Farm Implement)
A28Development Of Integrated Farm Center (Songhai Model) In Borno Central Senatorial District, Borno State
A29Development Of Integrated Farm Center (Songhai Model) In Yobe East Senatorial District, Yobe State
A30Development Of Gashua Irrigation Project (Irrigation Project Development, Procurement Of Tractor And Farm Implement)
A31Development Of Additional 255ha At Ngalda/Garin Gada Irrigation Project (Irrigation Project Development, Procurement Of Tractor And Farm Implement)
A32Development Of Additional 255ha At Gora Irrigation Project (Irrigation Project Development, Procurement Of Tractor And Farm Implement)
A33Development Of Additional 255ha At Michika Irrigation Project (Irrigation Project Development, Procurement Of Tractor And Farm Implement)
A34Construction Of 1No. Community Development Center At Abakire in Fune Lga, Yobe State
A35Conversion of Hand Pump Boreholes to Solar Powered in Potiskum Lga, Yobe State
A36Provision of 154nos. Tubewells For Irrigation At Fadama Areas Of Nangere Lga, Yobe State
A37Provision of 154nos. Tubewells For Irrigation At Fadama Areas Of Fika Lga, Yobe State
A382nos. Solar Powered Boreholes In Maiduguri Metropolitan Federal Constituency
A39Provision of 1No. Solar Powered Borehole with Reticulation in Unguwar Maigari Sale Dogon Marke, Garin Ila – Malammadori Lga,
A40Provision Of 21nos. Motorized Hand Pump Boreholes In Bauchi Central Senatorial District
A41Construction Of Solar Powered Boreholes Across Yobe North Senatorial District, Yobe State (Nguru, Jakusko & Karasuwa Lgas)
A42Construction Of Solar Powered Boreholes Across Yobe North Senatorial District, Yobe State (Bade, Yusufari & Machina Lgas)
A43Construction Of 2nos. Jumbo Solar Boreholes – 1No. Each At Gubio And Magumeri Lgas in Borno North Senatorial District.
A44Small Irrigation Schemes at Different Locations in Katsina South Senatorial District
A45Construction of Local Dyke/Embankment at Jigawa Village
A46Construction of 6 Ring Culverta Along Bida-Jigawa Road
A47Construction of Local Dyke/Embankment At Gabarwa Village
A48Construction of Local Dyke/Embankment At Yim Village
A49Construction of Local Dyke/Embankment At Tarja Village
A50Completion of Storage Facilities, Construction of Two Million Surface Tank and 1 Million Over Head Tank Complete with Accessories at Abari (Connection of Water Point to Houses)
A51Small Towns Water Supply Projects Across Borno North, Borno State (Construction of Middle Aquifer Boreholes at Damasak – Mobbar Lga)
A52Small Towns Water Supply Projects Across Borno North, Borno State (Construction Of Water Storage Facilities At Damasak – Mobbar Lga)
A53Small Towns Water Supply Projects Across Borno North. Borno State (Reticulation Works At Damasak – Mobbar Lga)
A54Supply and Installation Of 200nos. All-In-One Motion Sensor Solar Light At Boreholes Locations Across Borno North, Borno State
A55Construction of 10# Package of Solar Powered Boreholes with Complete Accessories In Oulani/Gujba/Damaturu/Tarmuwa Fed. Const. Yobe State; (Drilling of 3nos. Solar Powered Boreholes At Damaturu & Tarmuwa Lgas. Yobe State)
A56Construction of 10# Package Of Solar Powered Boreholes with Complete Accessories in Gulani/Gujba/Damaturu/Tarmuwa Fed. Const. Yobe State\; (Drilling Of 4nos. Solar Powered Boreholes At Gujba & Gulani Lgas, Yobe State).
A57Construction of 10# Package of Solar Powered Boreholes with Complete Accessories in Bursari/Geidam/Yunusari Fed. Const. Yobe State.
A58Construction Of 5# Package Of Solar Powered Boreholes with Complete Accessories in Potiskum Yobe State.
A59Construction of 5# Package of Solar Powered Boreholes with Complete Accessories in Nangere Yobe State.
A60Construction Of 10# Package Of Solar Powered Boreholes with Complete Accessories in Fune/Fika Fed. Const. Yobe State; (Drilling of 2nos. Solar Powered Boreholes At Fika Lga, Yobe State (Drilling of 3nos. Solar Powered Boreholes at Fika Lga, Yobe State)
A61Construction of 10# Package of Solar Powered Boreholes with Complete Accessories in Fune/Fika Fed. Const. Yobe State. (Drilling of 4nos. Solar Powered Boreholes at Fune Lga, Yobe State)
A62Construction of 5# Package of Solar Powered Boreholes with Complete Accessories in Bade Fed. Const. Yobe State.
A63Construction of 10# Package of Solar Powered Boreholes with Complete Accessories in Machina/Nguru/Karasuwa/Yusufari Fed. Const. Yobe State.
A64Construction Of 6 Classroom and Furniture At Community Islamic College Gad Aka, Fika Lga Yobe State

(B) GOODS

LOT BPROJECT DESCRIPTION
B1River Training and Channelization Works On Hadejia Jamaare Kumodugu Yobe River (HJKYR) (Procurement Of Ago)
B2River Training And Channelization Works On Hadejia Jamaare Kumodugu Yobe River (Hjkyr) (Procurement Of Lubricants And Services Filters For Heavy Duty And Earth Moving Machines)
B3River Training And Channelization Works On Hadejia Jamaare Kumodugu Yobe River (Hjkyr) (Procurement Of Lno. Excavator)
B4River Training And Channelization Works On Hadejia Jamaare Kumodugu Yobe River (Iijkyr) (Procurement Of Project Monitoring Vehicle
B5Renovation & Furnishing of 4nos. Blocks of Offices at Ahq & Liason Office (Procurement Of Liaison Office Furniture And Equipment)
B6Rehabilitation And Upgrading Of Equipment/Plants At Water Bottling Plant In Borno State (Procurement Of Distribution Vans & Trolleys
B7Procurement of High Discharge Irrigation Pumps (18” Centrifugal Pumps)
B8Upgrading Of ICT Center in Ahq (Supply Of Furniture and Equipment)
B8Upgrading of ICT Center in Ahq (Supply of Furniture and Equipment)
B9Rehabilitation / Replacement Of Heavy Duty Earth Moving Machines (Procurement Of Heavy Duty Earth Moving Machine)
B10Replacement of Farm Machines And Equipment (Procurement of Tractors /Farm Implement)
B11Replacement Of Heavy Duty Vehicles
B12Graduate Youth Capacity Building in Agric – Business ; Procurement Of Incubators, Hatchers And Feed Mills For Youth Empowerment In Agro Allied Business

CATEGORY (2) ZONAL INTERVENTION PROJECTS

(A) WORKS

LOT APROJECT DESCRIPTION
A1Land Clearing For Irrigation in Flood Plain Areas of Yobe State (Gogaram-Gagarachiya, Jakusko Lga, Yobe State)
A2Jumbo Solar Boreholes Across Borno North Senatorial District, Borno State (Construction Of 4nos. Solar Powered Boreholes; 2nos. At Mobbar-Damasak, 1No. At Marte And 1no. At Monguno Lgas.)
A3Jumbo Solar Boreholes Across Borno North Senatorial District, Borno State (Construction Of 4nos. Solar Powered Boreholes ; Lno Each At Nganzai, Gubio, Magumeri And Kaga-Benisheikh Lgas) A
A4Provision Of 2nos. 1Middle Acquifier And 1Lower Aquifier Boreholes Complete with Accessories At Ngazai Environs (Construction of 5nos. Deep Aquifer Boreholes With Accessories)
A5Storage Facilities, Construction Of 1Million Surface Tank and 500,000 Overhead Complete with Accessories at Ngazai (Construction of 1No. 750m3 Steel Elevated Surface Tank and 1No. 350m3 Steel Elevated Tank)
A6Complete Reticulation And Control Structures At Nganzai
A7Gajiram Water Scheme Reticulation Nganzai Borno State (Construction Of Water Works)

(B) GOODS

LOT APROJECT DESCRIPTION
B1Supply Of Bulldozer / Excavator To Gogaram Flood Plain Farming Communities (Procurement Of 1No. Excavator & 1No. Bulldozer)

(3.0) ELIGIBILITY REQUIREMENTS
Bidders are to provide the following documents as minimum requirement for consideration:

(3.1) FOR WORKS
(a) Evidence of Certificate of Incorporation issued by the Corporate Affairs Commission (CAC) including Form CAC 1.1 or CAC2 and CAC7;

(b) Last 3years (2018, 2019 & 2020) Tax Clearance Certificates valid till 31st December, 2021.

(c) Evidence of Registration on the National Database of Federal Contractors, Consultants, and Service Providers by submission of Interim Registration Report (IRR) expiring on 31/12/2021 or valid Certificate issued by BPP.

(d) Evidence of current compliance with Pension Reform Act 2004 by inclusion of PENCOM Compliance Certificate valid till 31st December 2021.

(e) Detailed company profile and organizational structure including Names and Telephone numbers of key Personnel (Technical / Managerial).

(f) Possession of experience as a Prime Contractor in at least three (3) projects of similar nature and complexity with verifiable letters of contract award and certificates of job completed within the last 3 years (to comply with this requirement, works quoted should be at least 70% physically completed).

(g) Having annual Auditors report for the last three(3) years (2018, 2019 & 2020) / Statement of affairs for pioneer company.

(h) For Joint Venture/Partnership, Memorandum of Understanding (MoU) should be provided (CAC, Tax Clearance Certificate, Pension Clearance Certificate, ITF Compliance Certificate, NSITF Clearance Certificate, IRR & Sworn Affidavit are compulsory for each JV partner).

(i) Evidence of Registration of Individual/company with relevant Professional bodies such as ARCON, COMEG, COREN or ICCON and IPAN, etc.

(j) Company’s Profile with the Curriculum Vitae of Key Staff to be deployed for the project, including copies of their Academic/Professional qualifications (in case of construction: COREN, QSRBN, ARCON, CORBON, etc.);

(k) Reference Letter from a reputable commercial bank in Nigeria, indicating willingness to provide credit facility for the execution of the project when needed;

(l) Bidders are to provide evidence of ownership/lease of relevant construction equipment;

(m) Possession of satisfactory Quality Assurance/Quality Control Manual

(n) Evidence of Current Compliance with Industrial Training Fund (ITF) Amendment Act 2011 by inclusion of Certificate of Compliance from Industrial Training Fund valid till 31st December 2021.

(o) Accompany bid document with Sworn Affidavit:-

(i) Disclosing whether or not any officer of the relevant committees of Chad Basin River Development Authority or the Bureau of Public Procurement is a former or present Director, shareholder or has any pecuniary interest in the bidder and to confirm that all information presented in its bid are true and correct in all particulars.

(ii) That the Director(s) of the firms has/have never been convicted in any court of law within or outside Nigeria.

(iii) That none of the company’s directors or the company itself is bankrupt.

(iv) That none of the officers of Chad Basin Development Authority or Bureau of Public Procurement is a former or present staff of the company.

(v) That the Company is not in receivership.

(p) Evidence of current Nigeria Social Insurance Trust Fund (NSITF) Compliance Certificate valid till 31st December 2021.

(q) All documents for submission must be transmitted with a signed Covering/Forwarding letter under the Company/Firm’s Letter Head Paper bearing amongst others, the Registration Number (RC) as issued by the Corporate Affairs Commission (CAC), Contact Address, Telephone Number (preferably GSM No.), and e-mail address. The Letterhead Paper must bear the Names and Nationalities of the Directors of the Company at the bottom of the page, duly signed by the authorized officer of the firm

NOTE that all documents/information required must be paginated, submitted in the Sequence/order as listed in a – p above. Non-compliance will lead to disqualification.

(3.2) FOR GOODS
(a) Evidence of Certificate of Incorporation issued by the Corporate Affairs Commission (CAC) including Form CAC 1.1 orCAC2 and CAC7;

(b) Last 3years (2018,2019 & 2020) Tax Clearance Certificates valid till 31st December, 2021.

(c) Evidence of Registration on the National Database of Federal Contractors, Consultants, and Service Providers by submission of Interim Registration Report (IRR) expiring on 31/12/2021 or valid Certificate issued by BPP.

(d) Evidence of current compliance with Pension Reform Act 2004 by inclusion of PENCOM Compliance Certificate valid till 31st December 2021.

(e) Detailed company profile and organizational structure including Names and Telephone numbers of key Personnel (Technical / Managerial).

(g) Having annual Auditors report for the last 3 years (2018, 2019 & 2020) / Statement of affairs for pioneer company.

(h) For Joint Venture/Partnership, Memorandum of Understanding (MoU) should be provided (CAC, Tax Clearance Certificate, Pension Clearance Certificate, ITF Compliance Certificate, NSITF Clearance Certificate, IRR & Sworn Affidavit are compulsory for each JV partner);

(i) Reference Letter from a reputable commercial bank in Nigeria, indicating willingness to provide credit facility for the execution of the project when needed;

(j) For Procurement of Motor Vehicles, only Companies included in the National Automotive Design and Development Council’s approved list of Local manufacturers of vehicles or their authorized representatives should bid for the procurements

(k) Possession of satisfactory Quality Assurance/Quality Control Manual

(l) Evidence of current compliance with Industrial Training Fund (ITF) Amendment Act 2011 by inclusion of Certificate of Compliance from Industrial Training Fund valid till 31st December 2021.

(m) Accompany bid document with Sworn Affidavit:-

(i) Disclosing whether or not any officer of the relevant committees of Chad Basin River Development Authority or the Bureau of Public Procurement is a former or present Director, shareholder or has any pecuniary interest in the bidder and to confirm that all information presented in its bid are true and correct in all particulars.

(ii) That the Director(s) of the firms has/have never been convicted in any court of law within or outside Nigeria.

(iii) That none of the company’s directors or the company itself is bankrupt.

(iv) That none of the officers of Chad Basin Development Authority or Bureau of Public Procurement is a former or present staff of the company.

(v) The Company is not in receivership.

(n) Evidence of current Nigeria Social Insurance Trust Fund (NSITF) Compliance Certificate valid till 31st December 2021;

(o) All documents for submission must be transmitted with a signed Covering/Forwarding letter under the Company/Firm’s Letter Head Paper bearing amongst others, the Registration Number (RC) as issued by the Corporate Affairs Commission (CAC), Contact Address, Telephone Number (preferably GSM No.), and e-mail address. The Letterhead Paper must bear the Names and Nationalities of the Directors of the Company at the bottom of the page, duly signed by the authorised officer of the firm.

NOTE that all documents/information required must be paginated, submitted in the Sequence/order as listed in a – n above. Non-compliance will lead to disqualification.

(4.0) COLLECTION OF TENDER DOCUMENTS
Interested companies are to collect the Standard Bidding Document (SBD) from the office of the (Head of Procurement Office, East Wing Ground Flour No. 48, Chad Basin Development Authority, Mohammed Lawan Building, Km 6, Dikwa Road, Maiduguri, Borno State) on evidence of payment of a non-refundable tender fee of N10,000.00 per Lot, paid into the (Chad Basin Development Authority)’s Remita account in any reputable commercial bank in Nigeria.

(5.0) SUBMISSION OF TENDER DOCUMENTS
Prospective bidders are to submit bid for each of the Lot desired, two (2) hard copies each of the technical and financial bids with softcopy of financial bid only in MS Excel format, packaged separately in sealed envelopes and clearly marked as “Technical Bid” or “Financial Bid”. Thereafter, put the two sealed envelopes together in a bigger sealed envelope addressed to (The Managing Director, Chad Basin Development Authority, Mohammed Lawan Building, Km 6, Dikwa Road, Maiduguri, Borno State.) and clearly marked with (the name of the project and the Lot number). Furthermore, the reverse of each sealed envelope should bear the name and address of the bidder and drop in the designated Tender Box at Open Registry of Chad Basin Development Authority not later than 12:00 noon on Monday, 5 July 2021.

(6.0) OPENING OF TECHNICAL BIDS
Only the technical bids will be opened immediately after the deadline for submission 12:00 noon on Monday, 5 July 2021 in the Conference Room, (Chad Basin Development Authority, Mohammed Lawan Building, Km 6, Dikwa Road, Maiduguri, Borno State), while the Financial bids will be kept un-opened. Please, ensure that you sign the Bid Submission Register in the office of (Head of Procurement Office, West Wing Ground Flour, Chad Basin Development Authority, Mohammed Lawan Building, Km 6, Dikwa Road, Maiduguri, Borno State), as the (Chad Basin Development Authority) will not be held liable for misplaced or wrongly submitted bids. For further inquiries, please contact the “08034443461 (Procurement)” on e-mail chadbasinmaiduguri@gmail.com

(7.0) GENERAL INFORMATION
(a) Bids must be in English Language and signed by an official authorized by the bidder;

(b) Bids submitted after the deadline for submission would be returned un-opened;

(c) Bidders should not bid for more than two (2) Lots

(d) All costs will be borne by the bidders;

(e) Presence of bidders/representatives and members of the public shall not be required during the bid opening ceremony in compliance with COMD-19 Guidelines. The Bids Opening will be covered by video recording (link will be sent to bidders) with the presence of two (2) representatives of private-sector professional bodies and Civil Society Organisation in the areas of Anti-Co rruption/Transparency and shall be made available to bidders upon request;

(f) Bid documents can also be collected in soft copies and Bidders can submit through Post (Courier Services);

(g) Only pre-qualified bidders at technical evaluation will be invited at a later date for financial bids opening, while the financial bids of un-successful bidders will be returned un-opened;

(h) The Chad Basin Development Authority is not bound to pre-qualify any bidder and reserves the right to annul the Procurement process at any time without incurring any liabilities in accordance with Section 28 of the Public Procurement Act 2007.

(i) This announcement is published for information purposes only and does not constitute an offer by the Authority to transact with any party for the project, nor does it constitute a commitment or obligation on the part of the Authority to procure services.

(j) Chad Basin Development Authority reserved the right to verify the authenticity of any claims on the documents submitted by companies.

(k) Chad Basin Development Authority reserved the right to verify the company address/location indicated in the expression of interest.

(l) Failure to comply strictly with instructions above and to provide any required documents may result in the disqualification of the company.

(m) Original documents shall be requested for sighting.

SIGNED
ABBA. GARBA; MNSE, MNIAE
MANAGING DIRECTOR/CEO