DEADLINE: 20TH APRIL, 2023
JIGAWA STATE GOVERNMENT OF NIGERIA
INVITATION TO TENDER FOR PRE-QUALIFICATION/FINANCIAL BIDS FOR THE PROCUREMENT OF UBEC/SUBEB 3RD & 4TH QUARTERS 2022 INTERVENTION PROJECTS

(1) INTRODUCTION:
The Jigawa State Universal Basic Education Board (SUBEB), wishes to invite reputable contractors with proven experience, reliability and capacity to submit pre-qualification documents for procurement of civil works and classrooms furniture across the State.

PROJECT SCOPE:

LOT NO.PROJECTSLOCATIONSLGEADURATION
1Construction of ECCDE Classroom blockK/Hausa SPSK/Hausa12 Weeks
2Construction of ECCDE Classroom blockSabon GidaRingini12 Weeks
3Construction of 3 Classroom with OfficeJarmariK/Kasmrna12 Weeks
4Construction of 3 Classroom with Office Sindimina JASSB/Kudu12 Weeks
Construction of 3 Classroom NormalGuri YammaGuri
5Construction of 2 Blocks each of 3 Classroom NormalGDJASS JinginoGwaram12 Weeks
Kwandigo P.SGwaram
6Construction of 2 Classroom with OfficeAlayeK/Kasamrna12 Weeks
7Construction of 2 Classroom with OfficeJSS KiyawaKiyawa12 Weeks
8Construction of 2 Classroom with OfficeK/GanjiGarki12 Weeks
9Construction of 2 Classroom with OfficeJigawa Isl.Babura12 Weeks
10Construction of 2 Classroom with OfficeMaigaiari JASSMaigatari12 Weeks
11AConstruction of 2 Classroom NormalGangoruB/Kudu10 Weeks
11BConstruction of 2 Classroom NormalAI-Islamaus alim Isl.B/Kudu10 Weeks
12Construction of 3 blocks each of 2 Classroom NormalJaya Nom,Garki12 Weeks
JASS KoreGarki
Babaus SPSBataira
13Construction of 2 blocks each of 2 Classroom NormalKurno P.SGwaram10 Weeks
N/KiguduGwaram
14Construction of 3 blocks each of 2 Classroom Normal Birniwa Model Sci.Birniwa10 Weeks
Tsamiya GomaK/Kasamma
KalwariK/Kasamma
15Construction of 2 blocks each of 3 Classroom with OfficeG/Gudinya JSSBabura12 Weeks
Riyadul Qur’anK/Hausa
16Construction of 3 Classroom NormalKawaya JSSBuji12 Weeks
17Construction of 3 Classroom NormalJASS FandumK/Kasamma12 Weeks
18Construction of 3 Classroom NormalS/Jawo JSSKazaure12 Weeks
19AConstruction of 2 Classroom with OfficeRuwan DawaJahun12 Weeks
19BConstruction of 2 Classroom with OfficeGaskawaJahun12 Weeks
20Construction of 2 Classroom with OfficeSabaturiDutse12 Weeks
21Construction of 2 Classroom with OfficeBulama IdiMaigatari12 Weeks
22Construction of 2 Classroom with OfficeNTA QuartersM/Madori12 Weeks
23AConstruction of 2 Classroom NormalGantsaBuji12 Weeks
23BConstruction of 2 Classroom NormalFagojiDutse12 Weeks
23CConstruction of 2 Classroom NormalKurnaGwaram12 Weeks
24Construction of 2 blocks each of Classroom NormalU/DinyaRoni12 Weeks
UmarniS/Tankarkar
25Construction of Wall FenceSambo P.SHadejia12 Weeks
26Construction of 4 Cubicle Vip ToiletK/TsuruMaigatari12 Weeks
Construction of 4 Cubicle Vip ToiletK/GanjiGarki
Construction of 4 Cubicle Vip ToiletAminu SuleRingim
27Construction of 4 Cubicle Vip ToiletJSS TanraTaura12 Weeks
Construction of 4 Cubicle Vip ToiletJASS KiriTaura
Construction of 4 Cubicle Vip ToiletJSS MajeTaura
Construction of 4 Cubicle Vip ToiletJSS Dr. SayyadiRingim
28Construction of 4 Cubicle Vip ToiletChamo JASSDutse12 Weeks
Construction of 4 Cubicle Vip ToiletNTA QuartersM/Madori
Construction of 4 Cubicle Vip ToiletKantin WajeHadejia
Construction of 4 Cubicle Vip ToiletU/DinyaRoni
Construction of 4 Cubicle Vip ToiletYandarinan Isl.K/Hausa
29Construction of 4 Cubicle Vip ToiletBabura Kudu JSSBabura12 Weeks
Construction of 4 Cubicle Vip ToiletAujara JASSJahun
Construction of 4 Cubicle Vip ToiletSakwaya JASSDutse
Construction of 4 Cubicle Vip ToiletSindimina JASSB/Kudu
30Construction of Handpump BoreholeYandannan Isl.K/Hausa6 Weeks
31Construction of Handpump BoreholeAminu Usman PSGumel6 Weeks
32Construction of Handpump Borehole K/Ganji Garki12 Weeks
Construction of Handpump BoreholeFatawa P.SRingim
Construction of Handpump BoreholeSimilmawa P.SRingim
Construction of Handpump BoreholeKuliumiRingim
Construction of Handpump BoreholeDanzomo Isl.S/Tankarkar
Construction of Handpump BoreholeDandaro NPSS/Tankarkar
33Construction of Handpump BoreholeJSS MajeTaura 12 Weeks
Construction of Handpump BoreholeJSS TsabareRingim
Construction of Handpump BoreholeKaraftayiKazaure
Construction of Handpump BoreholeDanfaruntama PSGumel
Construction of Handpump BoreholeArkiM/Madori
34Construction of Handpump BoreholeGadadinDutse12 Weeks
Construction of Handpump BoreholeNTA QuartersM/Madori
Construction of Handpump BoreholeKantin WajeHadejia
Construction of Handpump BoreholeJASS TauraTauru
Construction of Handpump BoreholeBadaweri PSBuji
Construction of Handpump BoreholeRiyadul Qur’anK/Hausa
35Construction of Handpump BoreholeSindimina JASSB/Kudu12 Weeks
Construction of Handpump BoreholeJASS KiriTaura
Construction of Handpump BoreholeNonumawa BurRoni
Construction of Handpump BoreholeFada IslamiyyaGumel
Construction of Handpump BoreholeMai HassanMaigatari
36Procurement of Covid-19 Materials and EquipmentSee ListSee List6Weeks
37Procurement of Covid-19 Materials and EquipmentSee ListSee List6Weeks
38Renovation of 1 block of 2 ClassroomsKadomaJahun8 Weeks
39Renovation of 1 block of 2 ClassroomsKukumaBuji8 Weeks
40Renovation of 5 blocks of 10 ClassroomsAdamu Kwano Isl.Hadejia12 Weeks
41Renovation of 5 blocks each of 6 ClassroomsAdamu MajeHadejia12 Weeks
Renovation of 5 blocks each of 6 ClassroomsAbu Ubaidah Isl.Hadejia
Renovation of 5 blocks each of 6 ClassroomsHaruna P.SHadejia
42Renovation of 5 blocks of 10 ClassroomsGarin Gabas PSM/Madori10Weeks
43Renovation of 1 block of 2 ClassroomsGwiram SahuwaGwaram12 Weeks
Renovation of 1 block of 2 ClassroomsJikasGwaram
44Renovation of 2 block of 2 ClassroomsM/BikiBabura8 Weeks
45Renovation of 1 block of 2 ClassroomsRoni ArewaRoni12 Weeks
Renovation of 1 block of 2 ClassroomsBilias TuntuboRoni
46Renovation of 1 block of 2 ClassroomsZarenawaB/Kudu12 Weeks
Renovation of 1 block of 2 ClassroomsZarenaB/Kudu
Renovation of 1 block of 2 ClassroomsZarenaB/Kudu
47Renovation of 1 block of 2 ClassroomsKaugama  Yamma    Kaugama12 Weeks
Renovation of 1 block of 2 ClassroomsHadinKaugama
Renovation of 2 block of 2 ClassroomsMuran   Auyo
48Renovation of 1 block of 2 ClassroomsU/MalamYankwashi12 Weeks
Renovation of 1 block of 3 ClassroomsK/WalawaYankwashi
49Renovation of 1 block of 2 ClassroomsBadoleGwiwa12 Weeks
Renovation of 1 block of 2 ClassroomsBazaraGwiwa
50Renovation of 1 block of 2 ClassroomsMiga GabasMigu12 Weeks 
Renovation of 1 block of 2 ClassroomsKoyaMiga
51Renovation of 1 block of 2 ClassroomsChirimbiBabura12 Weeks
Renovation of 2 block of 2 ClassroomsB/SarsS/Tankarkar
52Renovation of 1 block of 6 ClassroomsShagariKazaure12 Weeks
Renovation of 1 block of 2 ClassroomsShagariKazaure
53Renovation of 2 block of 2 Classrooms         Gumel Z/OfficeGumel12 Weeks
Renovation of 1 block of 6 Classrooms (UBE Type)Nasoro P.SGumel
54Renovation of 1 block of 2 ClassroomsJSS MaigatariMaigatari12 Weeks
Renovation of 1 block of 2 ClassroomsJobiMaigatari
55Renovation of 3 block of 2 ClassroomsG/MalamGagarawa12Weeks
Renovation of 3 block of 2 ClassroomsM/Madori ModelM/Madori
Renovation of 1 block each of 6 Classrooms (Storey)JSS KebindeBirniwa
Renovation of 1 block each of 6 Classrooms (Storey)DanmasaraDutse
56Procurement of 114 sets of ECCDE Classroom Furniture, consisting of a set of 4 single children plastic chairs (48/52/56cm) and 1 children plastic round tableSee ListSee List12Weeks            
 LGEASCHOOLQUANTITY
 BaburaBabura SPS12 Sets
 B/KuduB/Kudu Central12 Sets
 K/HausaK/Hausa SPS12 Sets
 RingimRingim S/Gida12 Sets
 GumelNasoro SPS12 Sets
 HadejiaShagari Community12 Sets
 DutseGalamawa SPS12 Sets
 KazaureKazaure Shagari12 Sets
 GumelDemonstration School8 Sets
 GwaramGwaram SPS5 Sets
 BimiwaBirniwa SPS5 Sets
57Procurement of 1,558 sets of 2 seater Primary 1-3 pupil FurnitureSCHOOLQUANTITY12Weeks                                 
 DutseGadadin P.S60 Sets
 DutseGadadin Sarki P.S60 Sets
 DutseJ/Tsada P.S60 Sets
 DutseKwaima P.S60 Sets
 KiyawaBalago P.S60 Sets
 KiyawaG/Adede P.S40 Sets
 KiyawaG/Bayi P.S40 Sets
 KiyawaMabara P.S40 Sets
 KiyawaTsotsawa P.S40 Sets
 S/TankarkarModoji P.S60 Sets
 S/TankarkarAyayaya P.S40 Sets
 B/KuduKanyar Gwadi60 Sets
 B/KuduLamido P.S60 Sets
 GwaramJikas P.S60 Sets
 GwaramFagam P.S60 Sets
 GwaramKwandu P.S60 Sets
 BujiMadabe P.S60 Sets
 BujiLalen Kudu P.S60 Sets
 BujiKarunjau P.S40 Sets
 JahunJahun Central60 Sets
 JahunTsalliya P.S40 Sets
 JahunAujaru SPS30 Sets
 JahunHardo Haruna40 Sets
 GagarawaGagarawa SPS40 Sets
 GagarawaYalawa P.S40 Sets
 GumelHammado P.S40 Sets
 S/TankarkarDan Yarda34 Sets
 K/HausaAska PS20 Sets
 KaugamaMarke Arewa60 Sets
 AuyoAuyo Central40 Sets
 AuyoAdaha PS20 Sets
 AuyoShawapa PS20 Sets
 AuyoKudigin PS40 Sets
58Procurement of 1,670 sets of 2 seater Primary 4-6 pupil FurnitureSCHOOLQUANTITY12 Weeks
HadejiaHadejia Mega School240 Sets
HadejiaHadejia Mega School240 Sets
DutseDutse Mega School240 Sets
KazaureKazaure Mega School240 Sets
KazaureKazaure Mega School240 Sets
K/HausaK/Hausa P.S40 Sets
K/KasaminaK/Kasamina P.S40 Sets
DutseKudai P.S40 Sets
BirniwaMasab P.S40 Sets
S/TankarkarU/Digawar Danzomo40 Sets
S/TankarkarDosono P.S40 Sets
K/HausaAska P.S40 Sets
K/HausaBalewa P.S40 Sets
K/HausaG/Chediya P.S30 Sets
GwaramMBPS Kila30 Sets
DutseInuwa Dutse H.E30 Sets
AuyoKafardau30 Sets
S/TankarkarAsayaya P.S30 Sets
59Procurement of 1,414 sets of 2 seater JSS Classroom FurnitureSCHOOLQUANTITY12 Weeks
B/KuduKwari P.S40 Sets
MigaWalawa P.S40 Sets
K/KasammaMadachi P.S40 Sets
B/KuduNalada P.S40 Sets
B/KuduGirls Only JSS40 Sets
AuyoAguma Yayawa40 Sets
M/MadoriShagari Isl.40 Sets
K/KasammaJajenu buru40 Sets
K/KasammaDadariya40 Sets
K/KasammaJiyan40 Sets
K/KasammaMailakauri40 Sets
KiyawaShawarin LPS40 Sets
KiyawaYolai P.S40 Sets
MaigarariJobi P.S40 Sets
MaigarariHaylin Dolai40 Sets
M/MadoriM/Madori Pilot40 Sets
JahunTsahiya P.S40 Sets
K/HausaYandarma Isl.40 Sets
DutseGaladanchi P.S40 Sets
RingimZ/Kaya40 Sets
RoniU/Dinya40 Sets
S/TankarkarMuku P.S40 Sets
S/TankarkarDauzomo SPS40 Sets
TauraGilima PS40 Sets
S/TankarkarU/Liman40 Sets
YankwashiFirji P.S40 Sets
YankwashiDankama P.S40 Sets
K/KasammaSinamu34 Sets
BaburaG/Gudinya60 Sets
KazaureS/Jawo JSS60 Sets
BujiJSS Kawaye60 Sets
K/KasammaJASS Fandum60 Sets
KazaureS/Jawo JSS60 Sets
60Procurement of 114 sets of ECCDE Classroom Furniture consist of set of 4 single children plastic chairs (48/52/56cm) and 1 children plastic round tableSCHOOLQUANTITY12Weeks   
 MigaAgufa P.S7 Sets
 JahunKwanjamawa7 Sets
 KiyawaKiyawa Central8 Sets
BujiYayarin Tukur7 Sets
S/TankarkarDanladi Central7 Sets
GagarawaGarin Chiroma7 Sets
MaigutariAlhassan Model7 Sets
RoniDansure P.S7 Sets
GwiwaTsubui P.S7 Sets
TauraMajia P.S7 Sets
GarkiGarki SPS7 Sets
M/MadoriG/Bundungoma8 Sets
GuriGuri Model7 Sets
AnyoG/Kuka7 Sets
K/KasammaK/Kasamma Special7 Sets
MigaDangyatin PS7 Sets
61Procurement of 1,557 sets of 2 seater Primary 1-3 pupil furnitureSCHOOLQUANTITY12 Weeks                    
BaburaKanya Babba40 Sets
B/KuduBabaidu U/Najaji40 Sets
BirniwaBirniwa SPS40 Sets
BirniwaDiginsa PS40 Sets
BujiSagu PS40 Sets
BujiY/Tukur Gabas PS40 Sets
DutseLimawa PS40 Sets
DusteKudai Gabas40 Sets
GagarawaDammadai PS40 Sets
GagarawaKanyu PS40 Sets
GarkiGarki SPS40 Sets
GarkiSiyori PS40 Sets
GumelDanama PS40 Sets
GumelSani A1 PS40 Sets
GuriDawa PS40 Sets
GuriGuri Model PS40 Sets
GwaramJikas PS40 Sets
GwaramGagaryaga PS40 Sets
 GwiwaTsulun Isl.40 Sets
 GwiwaGwiwa Isl.40 Sets
 HadejiaAgumau Isl. PS40 Sets
 JahunTaraya PS40 Sets
 JahunAujara PS40 Sets
 S/TankarkarAchigadi PS37 Sets
 K/KasammaAlaye P.S40 Sets
 BaburaJigawa Isl.40 Sets
 KiyawaJSS Kiyawa40 Sets
 MaigatariJASS Maigatari40 Sets
 GarkiK/Ganji40 Sets
 B/KuduGangara40 Sets.
 GwaramN/Kigudu40 Sets
 GarkiJaya NPS40 Sets
 K/KasammaKalwari PS40 Sets
 GwaramAl-Islamaris Alim40 Sets
 B/KuduJASS Kore40 Sets
 GarkiBaburu SPS40 Sets
 BaburaBirniwa Model Scl40 Sets
 AuyoKafardau P.S40 Sets
62Procurement of 1,670 sets of 2 seater Primary 4-6 pupil furnitureSCHOOLQUANTITY12 Weeks            
DutseBurtulan60 Sets
DutseKatangare60 Sets
DutseChamo Central60 Sets
B/KuduYakubu Pilot60 Sets
GqaramDoro PS60 Sets
GarkiDan barage40 Sets
GarkiK/Maikaho40 Sets
GarkiMuku P.S40 Sets
RingimTofia P.S40 Sets
RingimKijawal40 Sets
RingimKatufu60 Sets
GwaramKuma PS60 Sets
RingimAuramo40 Sets
TauraChukuto60 Sets
TauraJSS Gujungu60 Sets
GwaramMBPS Kila70 Sets
GwaramKila Kudu60 Sets
GuriGuri Model40 Sets
GuriGuri SPS60 Sets
B/KuduK/Maigwaram60 Sets
GwiwaZomo Mahuta40 Sets
GwiwaKoreyal PS40 Sets
GwiwaDabi PS40 Sets
YankwashiSabuwar Kanawa40 Sets
YankwashiUnguwar Liman40 Sets
YankwashiMaisaya30 Sets
RoniAmaiyawa Gada40 Sets
RoniKwaitu PS40 Sets
RoniBarinje40 Sets
JahunKwanjamawa60 Sets
JahunLili Gaburi40 Sets
JahunHarbo Central40 Sets
DutseJigawa Tsuda40 Sets
JahunKakuyawa SPS40 Sets
JahunAujura SPS30 Sets
63Procurement of 1,414 sets of 2 seater JSS Classroom furnitureSCHOOLQUANTITY 12 Weeks                 
 B/KuduJSS Zango40 Sets
 B/KuduJSS Zarenawa40 Sets
 S/TankarkarSule Arewa60 Sets
 S/TankarkarJSS B/Sara60 Sets
 S/TankarkarJSS Maifaru60 Sets
 B/KuduJSS Kantoga60 Sets
 B/KuduYakubu Pilot60 Sets
 B/KuduJSS B/Kudu60 Sets
 B/KuduJSS Katangare40 Sets
 GwaramJSS Nasarawa60 Sets
 GumelZango P.S40 Sets
 GumelGalagamma P.S40 Sets
 HadejiaKamin Waje P.S40 Sets
 KazaureShagari JSS60 Sets
 M/MadoriJSS Toni Kutara40 Sets
 K/HausaJSS K/Hausa60 Sets
 RoniJSS U/Ashe60 Sets
 KaugamaJSS U/Jibrin60 Sets
 KaugamaFadima Zahra Isl.40 Sets
 HadejiaJASS Garko40 Sets
 HadejiaSabuwa Shehu40 Sets
 GwaramJASS Gwaram60 Sets
 KiyawaJSS Katanga60 Sets
 DutseZainab Isl.60 Sets
 S/TankarkarJSS Sule40 Sets
 MaigatariDanmanomi P.S34 Sets
 BaburaGiginya Central40 Sets
 GumelDahiru Atta P.S30 Sets
 S/TankarkarDanyarda P.S10 Sets

All projects have a completion period of not later than 12 weeks.

(3) ELIGIBILITY REQUIREMENTS
To be considered for pre-qualification interested competent and reliable contractors are required to provide verifiable evidence including but not limited to the following documents:

(i) Certificate of incorporation with Cooperate Affairs Commission;

(ii) Evidence of registration with Jigawa State Works Registration Board;

(iii) Certified true copy of Memorandum and Article of Association;

(iv) Tax clearance certificate for the last three (3) years;

(v) Audited account for the last one (1) year;

(vi) VAT registration and evidence of past remittance;

(vii) Evidence of financial capability and banking support;

(viii) Company average annual turnover of N5,000,000.00 for bid price of less than N20,000,000.00 and turnover of N10,000,000 for bid price above N20,000,000.00

(ix) Evidence of similar project executed in the last five (5) years (letter of award and completion certificate);

(x) Verifiable evidence of company profile and technical qualification of key personnel registered with relevant professional bodies (COREN, CORBON, QSRBN, ARCON etc.);

(xi) That the company have fulfilled all obligations to pay taxes, pensions and social security contributions;

(xii) A sworn affidavit certifying as follows:

(a) That the document submitted for the pre-qualification exercises are not only genuine but correct.

(b) That none of the directors of the company has been convicted by any court of law.

(c) That the company is not bankrupt.

(d) That none of the officers of Jigawa State Local Government is a present or former director of the company.

(e) Any other relevant information that will help in determining the company’s suitability for the work;

  • Minimum of 2% Bid security in form of insurance bond is compulsory.
  • No alternative bid is allowed in the same lot.
  • No contractor is allowed to bid for more than three (3) lots.
  • Bidders with the same subsidiary relationship should not allowed to partake in the same lot.
  • Bid validity of 120 days.

(4) COLLECTION OF TENDER DOCUMENT
All contractors would be required to pay a non-refundable tender fee of N25,000.00 at the Account Department and collect tender documents from 10:00am to 2:00pm, which includes drawings, Bill of Quantities, SBD, and GCC at the office of Secretary Tender Board SUBEB Headquarter Dutse respectively.

However, all bidding documents could be obtained through Jigawa State E-Procurement portal (https://jigawa-eproc.eurodyn.com/epps/home.do)

(5) DOCUMENTATION AND SUBMISSION
Prospective bidders are to submit pre-qualification documents, two hard copies of the Technical and financial bids package in sealed envelopes. All completed bids should be spirally bound and submitted in (2) separate sealed envelopes, and each of these should consist of (1) original and (2) copies duly signed by the bidders’ Executive representative. The envelopes should be marked at the top left hand corner, pre-qualification and financial tender documents with the company name at the back and Lot no. clearly written on them, addressed and returned to the address below not later than 6 weeks from the date of this publication

NOTE that all completed bids should be sent through Jigawa State E-procurement portal (https://jigawa-eproc.eurodyn.com/epps/home.do)

Note:
SUBEB reserves the right to accept or reject any application at any time without incurring any liability.

All expenses incurred as a result of preparation and submission of documents for this exercise shall be borne by the interested company (non-refundable fee). The Bid will be electronically opened on 20 April, 2023 by 12:00noon.  However, the exercise will be projected at the Board’s Conference hall at SUBEB Headquarter Dutse.

SIGNED:
SECRETARY TENDER BOARD
JIGAWA STATE UNIVERSAL BASIC EDUCATION BOARD, DUTSE