DEADLINE: 30TH NOVEMBER, 2025
ACTIVE SUPPORT FOR RURAL PEOPLE INITIATIVE (ASURPI)
REQUESTING FOR YOUR QUOTATION FOR THE REHABILITATION OF SOLAR POWERED BOREHOLE
ASURPI Is Requesting for your quotation on your company letter headed paper for the REHABILITATION OF SOLAR POWERED BOREHOLE of the below item.
| S/N | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| A | PRELIMINARY | ||||
| A1.1 | Initial Mobilization and final Demobilization of equipment and personnel. | LS | 1 | ||
| A1.2 | Clearing of site on completion of the project. | LS | 1 | ||
| B | BOREHOLE REPAIR | ||||
| B1.1 | Gravel Pack & Cement Grouting (Sealing for durability) | UNIT | 1 | ||
| B1.2 | Borehole flushing (Air lifting or backwashing using surge block or compressor ) for 4 hour, use of pressure sflushing, till the boreholes is silt free | Nr | 4 | ||
| B1.3 | Conduct continuous borehole pump test for not less than 8 hour period. | HRS | 4 | ||
| B1.4 | Conduct water quality analysis to include for biological, chemical and physical | Nr | 1 | ||
| B1.5 | Allow for the disinfection of the borehole with the approved chemical | Nr | 1 | ||
| B1.6 | Allow for the supply and installation of 150mm steel well head include Flow meter, Non Return Valve and Gate valve | Nr | 1 |
| S/N | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| C | SOLAR PUMP AND POWER REQUIREMENTS | ||||
| C1.1 | Allow for the provision and installation of Riser pipes 35mm dia include other accessories as directed by the Engineer. | m | 60 | ||
| C1.2 | Supply and installation of Solar Pump (SQF 2.5-2 with CU200 controller) | Nr | 1 | ||
| C1.3 | Supply and Install Solar monovoltaic Panels 300watts,complete with accessories to be executed as approved by the Engineers Representative | Nr | 4 | ||
| C1.4 | Supply and installation of 3 x 6mm2 pump cable, joint ket, earthing and associated Structures | Nr | 1 | ||
| C1.5 | Construction of panel support structure to accommodate all the panels mounted on the top of the tank Including brazing with angle Iron to avert vandalizations | LS | 1 | ||
| C1.6 | Supply and install locally assembled lightening protection set with hard drawn high conductivity copper tape of 1 x 3mm | Set | 1 | ||
| D | Construction 600l of Elevated Storage Tank | ||||
| D1.1 | Allow for the rehabilitation/construction and erection of 6m steel stanchion to include for excavation, concrete works, reinforcment,treat with 1 coats of red oxide and apply 2 coats of approved paint on stanchion and walkway and hand rails. | Nr | 1 | ||
| D1.2 | Allow for the provision for pipes work for the inlet and out let connections | LS | 1 | ||
| D1.3 | Supply and install approoved 3000L x2 black GP/PVC tank and complete with technical work | 1 | 2 | ||
| E | RECTICULATION : | ||||
| E1.1 | Excavate trench 300mmx300mm to receiver upvc water distribution pipes from the bore hole over head tank inlet location. | LS | 1 | ||
| E1.2 | Supply and lay 32mm dia water inlet upvc pipes from the borehole location to tank, complete with accessories | m | 10 | ||
| E1.3 | Excavate trench (300mmx300mm) and lay 50mm upvc pressure pipe from tank to tapisland | m | 70 | ||
| E1.4 | Island/Water Shop (Disability & Gender Inclusive) with inspection chambers (for the reticulation), control valve chambers, drainages and soak pit. | Nr | 1 | ||
| F | PERIMETER FENCING-7mx7m | ||||
| F1.1 | Excavate trench to receive concrete in foundation starting from stripped level maximum depth not exceeding 1.0m | m² | 22.00 | ||
| F1.2 | Concrete Foundation trenches 230mm thick Grade 20-1.2.4. | m³ | 4.2 | ||
| F1.3 | 230mm thick hollow sandcrete block work in cement and sand mortar layed in stretcher bond filled solid with weak concrete 1:3:6-38mm aggreagte complete(Expansion joint double wall inclusive) | m² | 20 | ||
| F1.4 | Construction Chain link fence around the borehole anchored on GI pipes (poles) at intervals of 1500mm with a double leave gate. Supply and lay 150mm lateritic material and compacted then spread 18mm chippings after compaction. | LS | 1 | ||
| F1.5 | Construction a steel box 750mmx750mmx750mm with 100mm thick concrete cover as approved by engr. for safety protection to the bore hole | LS | 1 | ||
| F1.6 | Parameter fencing of borehole using fence wire (2*2 Inch galvanized wire mesh ) of 2m high 18m2 span and barb wire. Proovied entrance dor poles, fittingand furnishing the floor with gravels | LS | 1 | ||
| F1.7 | Construction of a disability inclusive accessible ramp with hhand rail around the collection point (1:15cm) gradient slope with 15 cm allowance from the taps to be situated 100 meter away from the water facility. | LS | 1 | ||
| F1.8 | Provide and fix (1000mx600mm) project signboad using weather – resistant metal and painted with white and red for visibility. It will display CBM, ASURPI and German Cooperation logos. Starnding 64inches tall | LS | 1 |
NOTE: 1 in Marafa community in Fakai LGA, 1 In Sakace community in Shanga LGA and 1 in Rikoto in Zuru LGA. Include unit price for each item and total cost.
Your company account details and TIN should be indicated in your quotation.
Note: 5% WHT will be deducted from the total amount and remitted to relevant tax authority in favour of your company.
Interested vendors should note the following:
Prepare and submit QUOTATION
1. Electronic submission: asurpkebbi2007@gmail.com
2. Physical submission: the above documents should be in a sealed envelope and dropped in the organization address below:
3. Please Attach your company profile
4. ACTIVE SUPPORT FOR RURAL PEOPLE INITIATIVE (ASURPI)No. 66, Guava road Gesse Phase 1 Birnin Kebbi, Kebbi State, Nigeria.
Closing date for submission of bid: 30th NOV, 2025