DEADLINE: 14TH APRIL, 2023
IKEJA ELECTRIC PLC (IE)
EXPRESSION OF INTEREST FOR 2022/2023 CAPITAL PROJECTS

(1.0) INTRODUCTION
Ikeja Electric Plc (IE) has received a CREDIT facility from the Central Bank of Nigeria (CBN) for Accelerated Transmission – Distribution Interface Projects to invest in the DISCOS through rehabilitation and expansion projects.

(2.0) SCOPE OF WORK

(2.1) IKEDC 44: Standardization of top 20% of Substations (Fencing of High Risk Distribution Transformers across the 6 Business Units within Ikeja Electric Plc franchise Area)

(1) Excavation of trenches.

(2) Application of concrete footing to receive 9-inch block wall.

(3) Setting of 9-inch block for dwarf block wall.

(4) Infill 9-inch block with weak concrete

(5) Installation of 50mm galvanized steel pipe into dwarf block wall

(6) Fixing and installation of gate (1200mm width-double leave)

(7) Welding with 50mm galvanized steel pipe at the top of the pole.

(8) Installation of chain link wire mesh.

(9) Plastering of the dwarf block wall with cement mortar.

(10) Removal of Top Soil with substation perimeter

(11) Levelling and compaction of the substation perimeter fence with laterite.

(12) Application of sharp sand within the substation perimeter fence.

(13) Laying of Damp-proof membrane within the substation perimeter fence.

(14) Levelling of base with granite of 100mm thickness

(15) Painting the dwarf block wall with IE specified colour (Post office red and yellow).

(16) Earthing of all metal parts.

(17) Placement of danger sign.

(3.0) CONDITION FOR ELIGIBILITY
In order to be considered for pre-qualification, bidders for relevance in their areas of interest will be required to provide information on the following:

(a) Evidence of company registration (CAC Certificate, C02, C07 or Statement of Affairs for Business Names).

(b) Detailed company profile including details of key professional staff.

(c) Bank Reference Letter

(d) Proof of Address

(e) Preceding 3 years Audited Accounts / Statement of Accounts.

(f) Preceding 3 years ended financial Tax Clearance Certificate (2019 2020, 2021)

(g) VAT Registration Certificate and evidence of VAT remittances.

(h) Evidence of Compliance with Pension Act, NSITF, ITF and evidence of remittances.

(i) Evidence of manufacturers accreditation (if applicable)

(j) Evidence of Corporate Social Responsibility (if applicable)

(k) Evidence of Corporate Environmental and Governance Policy (if applicable)

(l) Any other relevant supporting documents that would fast track the validation.

(4.0) SUBMISSION OF DOCUMENTS
Soft copies of all documents should be forwarded to Capitalprojects@ikejaelectric.com

All documents must be chronologically arranged as stated above, properly scanned as one document, and the email caption should be “EXPRESSION OF INTEREST FOR IKEDC 44 2022 / 2023 PROJECTS” with email signature stating the full name of the company, mailing address, mobile number, company representative and position.

All EOI documents must be submitted to the designated mail on or before close of business on Friday, 14 April, 2023.

(5.0) NOTE:

  • All information must be provided in the English Language
  • The Bid Documents will be sent to only eligible companies
  • This Advertisement shall not be construed as a commitment on the part of IE to enter any contractual relationship.

SIGNED
MANAGEMENT.

For enquiries and complaints, please contact our customer care helplines (01-7000250 and 01-2272940) or send an email to customercare@ikejaelectric.com

You can also reach us on our social media handles below.

Facebook: Ikeja Electric Plc

Twitter/Instragram: ikejaelectric/ieserve